Stations available for stakeout
You can customize the stations available for stakeout in an RXL, LandXML, or 12da road when staking a:
-
Station on string
-
Skew offset
To customize the stations available, select the stakeout method and then tap next to the Station field in the Stakeout screen. The Select station screen appears, listing the stations on the centerline.
Station interval settings
If required, edit the Station interval for lines and Station interval for arcs and transitions or accept the default value set when the road was defined. A separate station interval value for arcs and transitions enables you to tighten the interval for curves and more accurately represent the design on the ground.
Select the station interval Method:
-
The 0 based method is the default method and gives station values that are multiples of the station interval. For example, if the start station is 2.50 and the station interval is 10.00, the 0 based method produces stations at 2.50, 10.00, 20.00, 30.00 and so on.
-
The Relative method gives station values relative to the start station. For example, if the start station is 2.50 and the station interval is 10.00, the Relative method produces stations at 2.50, 12.50, 22.50, 32.50, and so on.
If you have configured different values for the Station interval for lines and the Station interval for arcs and transitions, then the list of available stations may include stations at different intervals.
In the Auto increment field:
-
Select Sta+ to automate the selection of the next station for stakeout.
-
Select Sta- to automate the selection of the previous station for stakeout.
-
Select No if you want to manually select the next station to stake.
Selecting Sta+ or Sta- in the Auto incrementfield provides a faster, more streamlined workflow.
Station interval settings (including Method and Auto increment settings) configured in the Select station screen are written to the road file so that the same settings are used if the file is shared with other survey crews. If the file is an IFC file, the Station interval settings are written to a Trimble Additional Properties (TAP) file. The TAP file is stored in the same folder as the IFC file of the same name. If other survey crews are using the IFC file, then you must share the .tap file with the .ifc file to ensure all survey crews use the same settings.
Available stations
To configure the types of stations shown in the station list, select the appropriate Available Stations check boxes.
Depending on the road type, you can select the following:
- Computed Sections defined by the station interval
- Horizontal Curve (key stations defined by the horizontal alignment)
- Vertical Curve (key stations defined by the vertical alignment)
- Template (stations where templates have been assigned)
- Super/Widen (stations where superelevation and widening has been assigned)
The station abbreviations used in the Roads software are:
Station type | Abbreviation | Meaning |
---|---|---|
Start/end | S | Start station |
E | End station | |
Computed sections | CXS | Computed sections defined by the station interval |
Vertical curve | VCS | Vertical curve start |
VCE | Vertical curve end | |
VPI | Vertical point of intersection | |
Hi | Vertical curve high point | |
Lo | Vertical curve low point | |
Superelevation/Widening | SES | Superelevation start |
SEM | Superelevation maximum | |
SEE | Superelevation end | |
WS | Widening start | |
WM | Widening maximum | |
WE | Widening end | |
Horizontal curve | PI | Point of intersection |
PT | Point of tangent (Curve to tangent) | |
PC | Point of curvature (Tangent to curve) | |
TS | Tangent to transition | |
ST | Transition to tangent | |
SS | Transition to transition | |
CS | Curve to transition | |
SC | Transition to curve | |
Template assignment | T | Template assignment |
Other | DXS | Design sections defined by the positions in the file |
STEQ | Station equation |